Tilbury Docks Cement Silo and Materials Extraction System
01/01/2008
Air Movement Systems Ltd has Installed the Extraction System Ducting at Tilbury Docks New Cement Silos, after the original supplier and contractors went into Liquidation.
Some of the ducting had been supplied but no drawings were available, AMS Ltd worked with the South American Projects office to design the required extraction duct systems to the Donaldson Cased Dalamatic units and identify existing parts which could be used and supplied the additional 3mm thick galavanised HG Ducting.
Air Movement Systems worked on-site with Fairport Engineering in December 2008 and worked on site through to July 2008.